| 16–25 Oct | Line 1 & 2 | Premier Blowers + ABS | 10 days | Lenney & Alex | Lines down. ABS on site 22–25th |
| 19–20 Oct | Line 1 | Overhaul | 2 days | Maintenance | |
| 19 Oct | Line 4 | Water ring fix | ~6 hours | Lenney & Alex | |
| 21 Oct | Duplex 1 | Overhaul | 1 day | Maintenance | |
| 26 Oct – 8 Nov | Line 1 | Airco NDC | 2 weeks | Kurt | 1 week install + 1 week startup. |
| 26–28 Oct | Line 8 | Overhaul | 3 days | Maintenance | |
| 26–28 Oct | PS8 | Overhaul | 3 days | Maintenance | |
| 29 Oct | Duplex 2 | Overhaul | 1 day | Maintenance | |
| 2–29 Nov | Line 6 | Airco NDC + Temp Control | 4 weeks | Kurt | 2 weeks install + 2 weeks startups. |
| 4–5 Nov | Line 9 | F847 trial | 2 days | Lenney & Alex | 2 orders (18 logs each — 62" and 72"). Special run. |
| 9–10 Nov | Line 6 | Overhaul | 2 days | Maintenance | |
| 9–10 Nov | Ply Splitter 6 | Overhaul | 2 days | Maintenance | |
| 23–24 Nov | Line 4 | Overhaul | 2 days | Maintenance | |
| 23–24 Nov | PS7 | Overhaul | 2 days | Maintenance | |
| 25 Nov | Rewind 2 | Overhaul | 1 day | Maintenance | |
| 30 Nov – 20 Dec | Line 7 | Temp Control upgrade | 3 weeks | Kurt | 2 weeks install + 1 week startup. |